P. 20

NOTE: Ensure an appropriately rated disconnect switch and circuit breaker (minimum 15 Amps and a SCCR of 5 kVA) are installed in a suitable and accessible location in accordance with the Applicable national and/or local codes (i.e. NFPA 70).
Step 4: Air Compressor Power Supply
The air compressor requires a dedicated power supply to prevent interaction with other equipment. Provide a means of power disconnect adjacent to the air compressor in accordance with manufacturer’s published instructions and in accordance with the applicable national and/or local codes (i.e. NFPA 70). The incoming power supply line is connected to the terminal block inside the NEMA 4 power supply box on the air compressor. Please consult the manual provided with each compressor for more details.
NOTE:
Confirm the available power source is compatible with the wiring configuration of the air compressor. Contact Johnson Controls if there is a discrepancy. Visit the CONTACT US page at www.tyco-fire.com for the contact information by location.
The auto-drain power supply can be connected to the nitrogen generator power supply.
  460v/3 phase or 208v/3 phase Landing Points
Labeled L1, L2, L3
  NOTE: Step 5:
Ensure an appropriately rated disconnect switch and circuit breaker (minimum 15 Amps and a SCCR of 5 kVA) are installed in a suitable and accessible location in accordance with the Applicable national and/or local codes (i.e. NFPA 70).
Plumb the Air Supply Line to Nitrogen Generator
Figure 2 – AMERICAS Power Supply Connections
 Connect the air discharge plumbing from the air compressor to the air inlet of the nitrogen generator using a minimum 1⁄2” black steel, galvanized steel, or copper lines. The air compressor start-up kit includes a flex-hose connection to be installed between the air compressor and nitrogen generator to reduce vibration.
Step 6a: Plumb the Nitrogen/Air Supply Line – No Additional Air Compressor (Figure 3a)
The nitrogen/air discharge plumbing from the TYCO Nitrogen Generator must be connected directly to the dry pipe or preaction valve trim using a minimum 1⁄2” black steel, galvanized steel, or copper lines. The size of the nitrogen/air supply line must be based on both the length of pipe between the nitrogen generator and fire sprinkler systems and the total volume of fire sprinkler systems being supplied.
TFP1275 Page 19 of 84